Ajaokuta Steel: 98% complete in 1994, and still no liquid steel

A steel plant is complete when it makes steel, not when its equipment is installed. What Ajaokuta teaches about how Nigeria measures strategic infrastructure.

RICITIES research · 10 min read

A blast furnace tower and its steel gantries at night, wreathed in steam
A working blast furnace at Donawitz, Austria. A unit like this sat at the heart of what Ajaokuta never commissioned. Not Ajaokuta.

The story of Ajaokuta Steel Company is not simply about an unfinished factory. It asks how a country measures whether strategic infrastructure is complete.

A steel plant is complete when its integrated production system can reliably turn raw materials into saleable steel at sustainable cost. The famous figure of 98% completion in 1994 is a historical claim about installation, not proof that the plant was 98% operational or able to make liquid steel.

01What 98% actually measured

The company’s own history says the figure referred to equipment erected, and that some completed units ran intermittently before shutting down for lack of funds. A 2022 academic study confirms the percentage was based on the weight of installed materials, not verified production capability.

MeasureWhat it establishesWhat it does not
Civil constructionBuildings and structures erectedProduction readiness
Equipment installationMachinery physically in placeMachinery tested and integrated
Mechanical completionInstalled to specificationSuccessful process commissioning
Operational commissioningSystems tested under loadSustained commercial production
Commercial operationSaleable product made consistentlyProfitability or long term viability
The 98% figure sits on the second row.

02Why it never made liquid steel

Integrated steel production chain · 1.3 million tonnes a year design target

  1. 01Iron oreExtraction and beneficiation at ItakpeOre needed beneficiation; furnace suitability questioned
  2. 02Rail and river portOre by rail, imported coking coal by riverExternal rail, road and port links not completed
  3. 03CokeCoke ovens prepare furnace fuelLocal coal unsuitable; imports required
  4. 04Blast furnaceIronmaking: the heart of the plantPart of the unfinished 2%, never commissioned
  5. 05SteelmakingBasic oxygen converters make liquid steel
  6. 06CastingContinuous casting into semi finished products
  7. 07RollingFinishing into saleable steel

Every later stage was installed to a high degree, but nothing downstream can run if the furnace and its supply chain do not. In an integrated plant, the last 2% can be the part that matters most.

Based on the 2022 academic study of the project and investigative reporting by ICIR. A simplified illustration.
  1. 01

    The missing 2% was not ordinary

    A former employee told ICIR the unfinished share included the blast furnace and auxiliary plants. A missing furnace or control system is not equivalent to an unfinished office block.

  2. 02

    Raw materials were never secured

    Ore needed beneficiation, local coal did not suit the coke process, imported coal needed a river port and Itakpe needed a dedicated railway. All were known at the planning stage.

  3. 03

    Outside infrastructure lagged

    A former sole administrator cited the absence of external roads, railway and supply infrastructure as a major obstacle to commissioning. A plant without its logistics is structurally incomplete.

  4. 04

    Funding and governance broke down

    Work halted at the end of 1983 when payments stopped. Disputes, political transitions and a 2000 to 2007 public private arrangement that ended in litigation followed.

  5. 05

    Technology aged in place

    Equipment designed in the 1970s cannot be assumed to meet today’s standards. Engineers say control systems in particular would need modernising or replacing.

03A conditional assessment

DimensionConcernCondition for revival
Physical assetsExtensive equipment installedAsset by asset condition audit
MetallurgyFurnace and auxiliaries not commissionedVerified furnace integrity and testing
Raw materialsBeneficiation and coking coalLong term supply contracts
LogisticsExternal connectivityWorking rail, port and freight
UtilitiesReliability unverifiedTested power, water and energy
TechnologyAgeing controls and equipmentModernise or replace where justified
GovernanceFunding and contract discontinuityOne accountable authority
CommercialNo sustained productionIndependent demand and cost study
EnvironmentLegacy industrial siteRemediation and compliance
WorkforceExisting expertiseUpdated training and readiness
A qualitative reading of documented challenges, not an audited engineering score.

04What Nigeria lost

  • Industrial value added: domestic minerals never became machinery, inputs and construction materials at scale.
  • Import dependence: manufacturers and builders kept relying on imported steel.
  • Industrial linkages: the expected ecosystem of engineering, fabrication, mining and maintenance did not emerge.
  • Infrastructure returns: rail, ports, energy and mining investments earned less without the plant they were meant to serve.

05Where it stands now

In September 2024 the Federal Ministry of Steel Development announced a memorandum of understanding with Tyazhpromexport, the original Russian builders, and consortium partners to rehabilitate, complete and operate Ajaokuta and the National Iron Ore Mining Company. It later said a full technical and financial audit was under way, and that a 2018 audit had found the plant generally robust apart from normal wear of replaceable parts, recommending automation of manual controls.

These are official statements. They are not evidence that the plant has been recommissioned or has produced liquid steel.

06From completion to production

  1. 01

    Independent technical and financial audit

    The real condition of every unit, utility and structure, with past spending, liabilities and contracts reconciled.

  2. 02

    Feasibility and technology review

    Is blast furnace and basic oxygen steelmaking still right, or does phased modernisation with alternative technology make more sense?

  3. 03

    Integrated infrastructure

    Beneficiation, rail, port, power, water, gas and industrial roads delivered with the plant, not after it.

  4. 04

    Phased commissioning

    Unit testing, stable integration, furnace commissioning, verified first liquid steel, then casting and rolling.

  5. 05

    Commercial operation

    Suppliers, customers, offtake, maintenance, workforce and downstream manufacturing partners.

Report thisWith this evidence
Equipment readinessIndependently certified operational equipment
CommissioningVerified first liquid steel
Capacity useOutput against installed capacity
QualityCompliance with steel standards
Raw materialsContracted and delivered volumes
EnergyMeasured power availability
CommercialSales, operating cost and cash
Environment and jobsEmissions, waste and water monitoring; jobs sustained
  1. POSCO, South Korea

    Long term industrial planning, technical capability and continuous efficiency investment.

  2. India

    Several production models, strong domestic demand and phased capacity growth.

  3. Duisburg, Germany

    Industrial clustering, specialised logistics and downstream manufacturing.

  4. Türkiye

    Port linked production tied to construction and export markets.

Sources

  1. 01Ajaokuta Steel Company Limited: company history
  2. 02The Ajaokuta Steel Project (2022), Springer Nature
  3. 03International Centre for Investigative Reporting: investigations into Ajaokuta and Itakpe
  4. 04Federal Ministry of Steel Development: announcements

Institutional engagement

Reviewing a stalled strategic project?

We help governments and investors separate physical progress from productive capacity, and plan the route from one to the other.

Keep reading

More from the knowledge centre

All research and insight
A fisherman casting a net from a canoe on Lagos Lagoon at dusk while another paddlesPerspective

Waterfront economies14 min read

The economics of inclusive, vibrant and resilient waterfronts

The best waterfront is not the one that maximises shoreline property values. It is the one that maximises participation, environmental performance and public value across the whole waterfront economy.

Read the perspective
Aerial view over the rooftops and streets of mainland LagosPerspective

Urban philosophy9 min read

Urbansophy: the six places of a healthy city

Why do we still build cities that fail the people in them? Our philosophy of the city, from its five components to the six places every settlement needs.

Read the perspective